2002 |
Nov. |
|
The ground-breaking ceremony was held. The expansion is to be finished in three phases. |
|
|
|
2003 |
Jun. |
|
The piling for plant foundation commissioned. |
|
|
|
2004 |
Jan. |
|
The civil foundation of process equipment started. |
May. |
|
The installation of process equipment started. |
Dec. |
|
The first coil was processed during commissioning of the pickling line.
The first coil was processed during commissioning of the first cold rolling mill. |
|
|
|
2005 |
Mar. |
|
The first coil was processed during commissioning of the first continuous pre-painting line.
The first coil was processed during commissioning of the first continuous hot-dip galvanizing line.
Expansion Phase I completed.
|
Oct. |
|
The second coil was processed during commissioning of the second cold rolling mill.
|
Dec. |
|
The second coil was processed during commissioning of the second continuous pre-painting line.
The second coil was processed duiring commissioning of the second continuous galvanizing line.
Expansion Phase II completed.
|
|
|
|
2006 |
Apr. |
|
The total investment increased from US$ 7,900 to US$ 10,000.
|
Oct. |
|
Sino Leading Technomaterial Co., Ltd was renamed to Yieh Phui (China) Technomaterial Co., Ltd.
|
Nov. |
|
The application to upgrade from CustomsClass B Enterprise to Class AA Enterprise was awarded.
The piling of plant in Phase III starts.
|
|
|
|
2007 |
Jan. |
|
Received ISO 9001:2008 certificate. |
|
|
|
2008 |
July. |
|
Received ISO 14001 and OHSAS 18001 certificate. |
Oct. |
|
Received IECQ QC 080000 HSPM Registered Firm. |
Nov. |
|
The total investment increased from US$ 231.3 million to US$ 321.3 million.and the regisreed capital raised from US$ 100 million to US$ 130 million. |
|
|
|
2009 |
Apr. |
|
The third coil was processed duiring commissioning of the third continuous galvanizing line.
|
|
|
Stage II (Expansion Phase III) was compeleted. |
Sept. |
|
Yieh Phui (China) obtained Indonesia Certificate SNI for coated steel. |
|
|
|
2010 |
Jun. |
|
The total investment increased from US$ 321.3 million to US$ 351.3 million and the regisreed capital raised from US$ 130 million to US$ 140 million.
|
Sep. |
|
Yieh Phui (China) obtained BC 1:2008, Singapore certificate. |
Oct. |
|
Shareholder of the company changed from MICKEY RIGENT INC to Yieh Phui (Hong Kong) Holidays Co.,Ltd. |
|
|
|
2011 |
Jun. |
|
Yieh Phui (China) obtained Malaysia MS Product Certification Licence for coated steel. |
|
|
|
2012 |
Jan. |
|
The total investment increased from US$ 351.3 million to US$ 449.3 million and the regisreed capital raised from US$ 140 million to US$ 172.66 million. |
Oct. |
|
Yieh Phui (China) obtained German KIII coating system certification for painted steel. |
|
|
|
2013 |
May. |
|
The total investment increased from US$ 449.3 million to US$ 547.3 million and the regisreed capital raised from US$ 172.66 million to US$ 205.32 million.
|
Sep. |
|
The total investment increased from US$ 547.3 million to US$ 631.8 million and the regisreed capital raised from US$ 205.32 million to US$ 233.5 million.
|
|
|
|
2014 |
Feb. |
|
YPC was award "Two Level Enterprise of Safety Production Standardization" issued by Administration of Work Safety of Jiang Su Province and executive-produced by State Administration of Work Safety.
|
Oct. |
|
YPC acquired authentication of the "High Tech Enterprise"
|
|
|
|
2015 |
Feb. |
|
YPC was awarded an authorized economic operator by Nanjing Customs, People's Republic of China.
The pickling and tandem cold mill commissioned. |
Mar. |
|
YPC acquired ISO/TS16949 quality management certification which applies to automotive-related products and service based on ISO 9001:2008. |
Aug. |
|
The Continuous Annealing Line commissioned. |
|
|
|
2016 |
Jan. |
|
YPC obtained JIS Mark certificate. |
Mar. |
|
YPC's laboratory was accredited as competent testing and calibration laboratory by CNAS (China National Accreditation Service). |
Jun. |
|
Total investment of YPC increased from US $ 631.8 million to US $ 639.8 million and the registered capital increased from US $ 233.5 million to US $ 236.2 million. |
Dec. |
|
YPC obtained ISO 50001 certificate. |
|
|
|
2017 |
Feb. |
|
The Third coil was processed during commissioning of the third continuous pre-painting line.
|
Dec. |
|
YPC reviewed by the authentication of the "High Tech Enterprise".
|
|
|
|
2018 |
Jan. |
|
The fourth continuous hot-dip galvanizing line commissioned.
|
Mar. |
|
YPC acquired new version certification of IATF 16949 quality management system which applies to automotive-related products and service.
Signed a "five-in-one" base cooperation framework agreement with Changshu Institute of Technology to comprehensively deepen industry-university-research cooperation.
|
|
|
|
2019 |
Aug. |
|
Passed the new version upgrade certification of IECQ QC080000 Hazardous Substance Process Management System requirements.
|
Dec. |
|
Passed the acceptance of demonstration enterprises in the model area of safety production standardization in Suzhou in 2019.
|
|
|
|
2020 |
Sept. |
|
Passed the new version transfer certification of ISO45001 Occupational Health And Safety Management System requirements
(The original OHSAS18001 System Certification is transferred to the new ISO45001 System Certification)
|
Nov. |
|
YPC was awarded an authorized economic operator by Nanjing Customs, People's Republic of China.( Recertification)
|
|
|
|